The repair list, line by line
What the largest items on the repair list are
Twenty-four lines hold half the dollars on PP&R’s 2023 repair list. This page says what each one is, where it came from and what has happened to it since.
Jump to · Where the numbers come from
- Where the numbers come from
- The 24 lines at a glance
- New construction from park plans: $102.2 million
- Building replacement or expansion, no study found: $88.3 million
- Overtaken by events: $41.0 million
- Repair of something in use: $57.6 million
- Repair mixed with upgrades: $22.4 million
- The other end of the list
- What follows from this
- What this page does not settle
- Where the numbers come from
- The 24 lines at a glance
- New construction from park plans: $102.2 million
- Building replacement or expansion, no study found: $88.3 million
- Overtaken by events: $41.0 million
- Repair of something in use: $57.6 million
- Repair mixed with upgrades: $22.4 million
- The other end of the list
- What follows from this
- What this page does not settle
Twenty-four lines make up half of the dollars on the repair list Portland Parks & Recreation (PP&R) released in 2023. The Atlas looked up what each one is. By its reading, about $58 million of that $311 million is repair of something that exists and is in use. The rest is new construction drawn from old plans, building replacements that have no study behind them, and lines that events have overtaken. At the other end of the list, 884 lines, three of every four, add up to $50 million. Reviewed November 16, 2026.
Where the numbers come from
The list. In November 2023 PP&R gave KGW News a list of 1,195 repair and improvement needs with a cost estimate for each. The estimates add up to $615.7 million. It is the only version of the list with a dollar figure on every line. The 1,195 rows · Repair costs by park
Status and growth. PP&R also publishes a current list without dollar figures. The Atlas used the October 2026 copy for two facts about each line: whether it is still open, and its "Growth %." Growth % is PP&R's own estimate of how much of a project adds capacity instead of fixing what exists. It matters because of how projects are paid for: see which money can pay for what. PP&R backlog map · Backlog priorities
The groups below are the Atlas's reading, made from PP&R's descriptions and the public record. PP&R has not reviewed them. A line can be a real need and still belong in a group other than "repair". Each group asks for a different kind of decision. None of this says the list is wrong. A list kept over many years, by many hands, gathers different kinds of needs; sorting them is meant to help the City and the community decide what to fund first.
The 24 lines at a glance
| Group | Lines | 2023 estimate | What it means |
|---|---|---|---|
| New construction from park plans | 8 | $102.2M | Plazas, visitor centers and trails proposed in plans from 2003 to 2018, with the plan's price scaled up |
| Building replacement or expansion, no study found | 3 | $88.3M | A rebuild, an expansion and a relocation, each entered as an idea |
| Overtaken by events | 4 | $41.0M | Closed on PP&R's own list, handed to another operator, or in a building the City voted to give away |
| Repair of something in use | 6 | $57.6M | Structural, seismic, surface and bridge work on assets people use now |
| Repair mixed with upgrades | 3 | $22.4M | Lines PP&R itself marks as half growth |
| Total | 24 | $311.4M | 50.6 percent of the list |
Fourteen of the 24 lines, worth $212.9 million, carry a Growth % of 50 on PP&R's current list.
New construction from park plans: $102.2 million
Eight lines come from four park plans. In each case the 2023 estimate equals the plan's own cost figure multiplied by a constant, which the Atlas worked out by division. None of the four plans came with committed funding.
Washington Park, four lines, $53.8 million. These are items from the 2018 Washington Park Master Plan Update, which the City Council accepted "as a guide" in March 2018. The plan prices everything at $94 million over more than 15 years and names possible sources without committing any.
| Line | 2023 estimate | What the plan describes |
|---|---|---|
| Visitor Centers | $22.5M | South Entry Garden Plaza, a new indoor garden and amphitheater upgrades, all in the plan's last phase (year 15 and later) |
| Staff Facility Improvements | $14.2M | A new natural areas maintenance building, a doubling of the existing maintenance facility, and a Rose Garden restroom and office upgrade |
| Playground and Recreation Improvements | $9.6M | A new Forest Canopy Walk in Hoyt Arboretum, last phase |
| Visitor Centers, Plaza Improvements, Food | $7.5M | Visitor centers, a café, entry courts and the Rose Garden Plaza |
The first phase of the South Entry was built between 2023 and 2024, paid from development charges, parking revenue and grants. The Atlas found no funding for the other items. Master plan · Council resolution 37348 · South Entry project
Waterfront Park, two lines, $28.8 million. These are two segments of the Waterfront Park Master Plan, written between 2000 and 2003. "Salmon Street Springs to Morrison Bridge" is the plan's Waterfront Plaza, priced at $7.5 million then and $21.0 million on the list: a new plaza with a deck over the river, an expanded dock and a repaved esplanade. "Hawthorne Bridge to Salmon Street Springs" was $2.8 million then and is $7.8 million on the list. PP&R first entered both in fiscal year 2004-05.
A new plan is now being drawn. In July 2026 PP&R opened an international design competition for the whole park, and Metro granted $750,000 toward it in October 2026. Whatever comes out of it will replace the 2003 scope these two lines still describe. 2003 master plan · Design competition · Metro, October 2026
Cathedral Park, one line, $10.4 million, and probably counted twice. The 2009 Cathedral Park Master Plan priced its improvements at $7.1 to $8.3 million across seven areas. The list carries six lines from 2009, one for each of six areas, which together come to $9.4 million. It also carries this single line from 2019, described only as "Cathedral Park MP Improvements," at $10.4 million. The Atlas found nothing that explains the second entry, and reads it as the same plan entered again. Cathedral Park Master Plan
River View Natural Area, one line, $9.3 million. This is the 2015 management plan for a natural area the City bought in 2011: new loop trails, seven bridges, two overlooks, road and parking work, and habitat restoration. The plan's total is $5.1 million, plus an optional $3.6 million pedestrian crossing of Highway 43. The line matches the two added together. Nothing here repairs an existing structure. River View management plan
Building replacement or expansion, no study found: $88.3 million
Montavilla Community Center, $46.4 million, the largest line on the list. The description reads, in full: "Rebuild or extensively renovate CC to meet current and future community needs. Look at pool needs at same time." It was entered in fiscal year 2009-10. The Atlas found no study, design or cost estimate behind it. The 2014 bond replaced the building's gym roof and heating and cooling units in 2018 and 2019. Montavilla bond project
Charles Jordan Community Center, $25.9 million. The line is titled "Expand facility; Develop strategy" and asks for a strategy for a pool or center expansion or relocation. Its description opens "$30M - Commissioner project." Since then the City has chosen to build the North Portland Aquatic Center at Northgate Park, with $91.5 million secured. That project delivers the indoor pool this line was reaching for. The line is still open. Whether it has been formally replaced, PP&R has not said. North Portland Aquatic Center
Community Music Center, $16.0 million. Titled "Expand and Relocate." The center is in a 1912 firehouse, and PP&R's own description says more analysis is needed to choose between renovating, rebuilding and moving. The 2023 list has a separate line for seismic and exterior work on the same building. Community Music Center
Overtaken by events: $41.0 million
Portland Tennis Center, $20.0 million. The line is "Replace tennis bubble with new structure": swap the air-supported dome over four courts for a permanent steel building. In August 2026 PP&R announced that USTA Pacific Northwest will lease and run the center and make "an initial investment of approximately $2.3 million," which covers a new dome, heating and cooling, a generator and roof work. The City keeps ownership and stays responsible for major capital work outside the agreement. The line is still open at $20 million for a steel building that is no longer the plan. The Atlas has not found a Council vote on the lease. PP&R announcement · Tennis Center review
Sellwood Community Center, $5.1 million. PP&R stopped running programs here in 2019, and a neighborhood nonprofit has operated the building since. In December 2025 the Council declared the property surplus and authorized selling it to that nonprofit. The line for its windows, heating and structural repairs is still open. Ordinance 192130
Charles Jordan roof, $10.7 million, and Multnomah Arts Center heating and cooling, $5.1 million. Both are marked closed on PP&R's current list. The roof line says it was funded by one-time General Fund money. The heating line calls itself a placeholder. Closed is PP&R's status and does not by itself show the work was done, but neither line is an open need by PP&R's own record.
Repair of something in use: $57.6 million
| Line | 2023 estimate | What it is | What has happened since |
|---|---|---|---|
| Southwest Community Center | $17.6M | Roof, structure, seismic and mechanical work on a 1999 building | Corroded roof supports found in March 2026; the pool closed in September 2026 for emergency repair |
| Matt Dishman Community Center | $13.8M | Seismic, windows, mechanical, electrical, pool roof | Entered in 2009. The 2014 bond renovated the pool in 2016 |
| Overlook House | $9.3M | Seismic upgrade of a 1928 brick house | No project found. The estimate is about $1,700 per square foot |
| East Delta Park turf | $6.0M | Replacing synthetic turf, a cost that returns about every ten years | Fields date from 2013 and 2014 |
| Gabriel Park tennis courts | $5.6M | Resurfacing, lights and fencing for six courts | About $940,000 a court |
| Springwater Corridor bridge | $5.2M | One of five lines for bridges rated poor in a 2021 assessment | Metro approved $2.75M for trail bridges in April 2026 |
The Southwest Community Center line is the clearest case of what a repair list is for: a rated defect, in a building open to the public, that became an emergency. PP&R, August 2026 · Dishman pool renovation · Metro, April 2026
Two of these estimates look high against the work described. For comparison, the four courts at Argay Park were rebuilt in 2017 with new fencing, lighting and drainage on a budget of about $1.07 million, roughly $270,000 a court, as a neighborhood paper reported at the time. The Atlas does not have the basis for either estimate and has asked. Mid-county Memo on Argay Park
Repair mixed with upgrades: $22.4 million
Multnomah Arts Center, Phase 2, $9.0 million. "General preventative maintenance plus service delivery and revenue generation upgrades" to the newer buildings.
Columbia Park fields, $8.3 million, and Clinton Park fields, $5.0 million. Both were entered in 2009. The descriptions say the fields "still need irrigation and improved goals," plus backstops and bleachers at Clinton. Columbia's line works out to about $2.8 million a field. In 2014 the City converted three grass fields at Delta Park to synthetic turf for about $4 million in total. The estimates are large for the work the descriptions name, and PP&R marks both lines as half growth. Delta Park turf contract, 2014
The other end of the list
The long tail is where most of the list's lines are, and little of its money.
| Slice of the 2023 list | Lines | Share of lines | Total |
|---|---|---|---|
| The 24 largest | 24 | 2 percent | $311.4M |
| The 884 smallest | 884 | 74 percent | $50.0M |
| Every line under $100,000 | 691 | 58 percent | $21.5M |
A caution on adding lines up: some lines overlap, as the Cathedral Park case shows, so the straight total of $615.7 million may overstate the list.
One small park as an example. Albert Kelly Park in southwest Portland has six lines totaling $1.57 million. The largest is $817,755 for "bridge replacement with a longer spanning wooden bridge (approx 30-40')" plus trail work and removal of a culvert in the creek. Two other lines, for field irrigation and paths, describe the same work as each other.
What follows from this
- The list mixes three kinds of decision. Fixing what is failing, replacing or enlarging a building, and building something a plan proposed are different choices with different payers. Development charges can pay for growth and cannot pay for repair. Which money can pay for what
- A repair total that includes all three overstates the repair problem and hides the building problem. Montavilla, Charles Jordan and the Community Music Center are decisions about whether to keep, rebuild or replace a center. They need a study and a vote, and a place on a list does not provide either.
- Some lines can come off now. Two are closed, one building is being sold, and one project has a new operator and a different plan.
What this page does not settle
- Current costs. These are 2023 estimates. PP&R has not published current figures line by line.
- The other 1,171 lines. The Atlas looked up the largest 24. It has not made the same check of the rest.
- How each estimate was built. The Atlas has asked PP&R for the basis of its estimates as part of a public records request. Records request
- Unconfirmed items. That the 2019 Cathedral Park line duplicates the six 2009 lines, and that the Charles Jordan expansion line has been replaced by the aquatic center, are the Atlas's inferences. That no study exists for Montavilla, the Community Music Center or Overlook House means only that the Atlas did not find one.
If PP&R or anyone else can correct a line here, the corrections page is the place to say so.