ParksAtlas

Try

Upkeep · PP&R's own figures

What existing sites are budgeted

What new parks cost to keep up

Portland Parks & Recreation expects the projects it is building or planning to add $9.5 million a year to its operating and maintenance costs by fiscal year 2029–30. One project, the North Portland indoor pool, is $6.4 million of that. For 32 of the 34 projects the figure is a placeholder: 3% of what the project costs to build.

The figures are from two workbooks PP&R gave City auditors in 2025: its operating and maintenance workbook for the FY 2025–26 budget, dated May 28, 2025 in the auditors' file, and its March 2025 answers about eight new projects. Audit Services shared both with the Atlas in November 2026. It does not endorse the Atlas or its analysis.

Read this first

The list is a forecast, and most of it is a rule of thumb

  1. Most figures are 3% of the building cost.PP&R told the auditors its policy is to use 3% of a project's funded cost as a placeholder until it works out a detailed estimate. Its workbook marks 32 of the 34 projects that way, each with a note that a detailed estimate is still needed.
  2. No money is attached to the list.The workbook calls these the next five years of requests, used to inform the bureau's forecast. The October 2025 City audit checked eight new projects and found that none had a funding plan for major maintenance or replacement (the audit's work paper).
  3. One project is two-thirds of the total.The North Portland indoor pool is listed at $6,407,000 a year: 3% of a $116.9 million project for the building, plus $2.9 million for utilities and operation. The workbook says it still needs an estimate based on the pool's business plan. The other 33 projects add $3.1 million.
  4. The workbook is from May 2025.Budgets, scopes and opening dates may have changed since. It also lists one project twice: new amenities at Columbia Park, at $54,000, in two different years with the same project number, so the total may count that amount twice.

5 projects have a second figure, and 4 of them differ

5 projects on the forecast list were also among the eight the auditors asked about in March 2025. For 3 of them PP&R supplied a worksheet that prices each amenity. The Old Town Skatepark worksheet, marked a first discussion draft, includes $541,494 a year for ranger services.

Yearly upkeep on PP&R's forecast list compared with the figure PP&R gave City auditors in March 2025, for projects on both
ProjectOn the forecast listGiven to auditorsBasis of the second figure
A new skatepark at Creston Park$150,000$96,400Worksheet, February 2025
A new park on the northernmost North Park Block$240,000$292,997Worksheet, 2023
A new park in Slabtown$150,000$150,000Placeholder; no estimate yet
Old Town Skatepark$450,000$869,702Worksheet, March 2025 (draft)
New amenities at University Park$54,000$96,000Placeholder; no estimate yet

The rates

The yearly cost PP&R assigns to each amenity

When PP&R prices a new park in detail, it counts what the park will have and multiplies each amenity by a yearly rate. These are the rates in the worksheets it gave the auditors. They are averages for estimating new sites, and the worksheet divides each one among the crews that would do the work: the park's zone crew, irrigation, turf, structures, heavy equipment and others. They do not show what any existing park receives.

PP&R's yearly operating and maintenance rate for each amenity, at fiscal year 2021–22 and 2025–26 values
Amenity and unitFY 2021–22FY 2025–26
Restroomeach$38,557$43,246
Play areaeach$13,668$15,331
Spray play featureeach$69,622$78,088
Sports courteach$6,104$6,846
Sports fieldeach$28,324$31,768
Skateparkeach$56,147$62,975
Reservable picnic areaeach$18,342$20,572
Dog off-leash areaeach$35,644$39,978
Community gardeneach$19,438$21,802
Open turf1per acre$11,103$12,453
Plazaeach$42,762$47,963
Bridge2of project cost3%3%
Treesper acre$684$768
Habitat preserve3unit not stated$679$762
Soft-surface trailper foot$1.38$1.55
Paved trailper foot$2.11$2.37
Overlook or viewing areaeach$8,127$9,115
Wayfinding sign or markereach$385$432
Interpretive sign or facilityeach$3,076$3,450
Trailheadeach$5,550$6,225
Facility4unit not stated$46,185$51,801
Natural area5per acre$945$12,453
Developed parkper acre$14,708$16,496
  1. 1. Open turf: The worksheet counts open turf as 30% of a developed park.
  2. 2. Bridge: No flat rate: 3% of the project's cost.
  3. 3. Habitat preserve: The worksheet does not say what one unit is.
  4. 4. Facility: The worksheet does not say what counts as a facility.
  5. 5. Natural area: The FY 2025-26 worksheet prices a natural-area acre like open turf. Its label reads "proxy Open Turf, due to Homeless and Climate Issues."

One rate rose thirteenfold.Every rate went up 12.2% between the two worksheets except the one for a natural-area acre, which went from $945 to $12,453, the same as an acre of open turf.

PP&R is using the higher rate.4 of the additions PP&R entered in its FY 2025–26 budget are natural-area land, and each is priced at its acreage times $12,453. They are listed below.

Upkeep is one of three yearly costs.PP&R told the auditors it also calculates two more yearly costs for each budgeted project: 3% of the project's cost for major maintenance, and the cost divided by the asset's useful life for replacement. For Parklane Park, a $29.7 million project, its three figures come to $3.1 million a year: $706,365 to operate and maintain it, $891,000 for major maintenance and $1,485,000 toward replacement.

How a worksheet adds up: Mill Park development, September 2022

PP&R's September 2022 worksheet for Mill Park: each amenity, how many, and its yearly operating and maintenance cost
Line on PP&R's worksheetCountA year
Rest rooms1$43,257
Play Areas1$15,335
Spray Play1$78,108
Sports Fields2$63,553
Reservable Picnic Areas1$20,578
Community Gardens1$21,808
Open Turf Acres (30% of Developed Parks)4$49,826
Plazas1$47,975
Trees (per acre)5.7$4,376
Soft Surface Trails (O&M per lf)2,000$3,102
Paved Trails (O&M per lf)10,500$24,878
Wayfinding Signs & Markers30$12,971
Facilities1$51,814
Developed Park Acre5.7$94,052
Total$531,632

Counts are acres for turf, trees and developed park, and linear feet for trails. The worksheets for the other five projects are in the downloads below.

The forecast list

34 projects, $9.5 million a year by 2029–30

Each project is listed under the fiscal year PP&R expects to ask for its upkeep money. 92% of the total is for projects built only with system development charges (SDCs), the fees on new development. Those fees can pay to build added capacity. They cannot pay to run it.

PP&R's forecast of new yearly operating and maintenance requests by fiscal year, with how each figure was set and what pays to build the project
ProjectUpkeep a yearHow the figure was setBuilt with
FY 2026–27$766,617
Extending the North Portland Greenway Trail into Kelley Point ParkKelley Point Park$81,3393% of $2.7 millionMetro
A new skatepark at Creston ParkCreston Park$150,0003% of $5 millionSDCs
A pedestrian and bike bridge over Columbia Boulevard, starting in Chimney Park on the Peninsula Crossing TrailChimney ParkPeninsula Crossing Trail$100,000Another site's costSDCs
The Red Electric Trail between the former Alpenrose Dairy and the Hayhurst neighborhood$31,5003% of $1.1 millionSDCs and a grant
A trail connection from Marshall Park to Tryon Creek State ParkMarshall Park$21,0003% of $700,000SDCs
A playground renovation, basketball court, lighting, walkways and a restroom at George ParkGeorge Park$90,0003% of $3 millionSDCs
Picnic areas, parking, paths, a restroom and utilities at Kelley Point ParkKelley Point Park$210,0003% of $7 millionSDCs
A walking loop, parking and access improvements at Rose City Golf CourseRose City Golf Course$82,778A drafted estimateSDCs and Metro
FY 2027–28$534,000
A master plan, trails and park amenities at the Wilkes Headwaters propertyWilkes Headwaters Property$240,0003% of $8 millionSDCs and Metro
A new park on the northernmost North Park Block, now a parking lotNorth Park Blocks$240,0003% of $8 millionSDCs
New amenities at Columbia Park, to be chosen with the publicColumbia Park$54,0003% of $1.8 millionSDCs
FY 2028–29$479,840
A new park in Slabtown, between NW 20th and NW 21st avenues$150,0003% of $5 millionSDCs
Converting the Wellington Park wading pool to a splash padWellington Park$36,0003% of $1.2 millionSDCs
Repairs in Forest Park to keep fire and safety access openForest Park$49,2753% of $1.6 millionMajor maintenance
Trail, fire lane, culvert, bridge and trailhead renovations in Forest ParkForest Park$90,0003% of $3 millionMetro
The North Portland Greenway Trail from Chimney Park to Cathedral ParkChimney ParkCathedral Park$64,4153% of $2.1 millionSDCs and Metro
The playground at Portland Heights ParkPortland Heights Park$18,0003% of $600,000Major maintenance
A trailhead on the Springwater Corridor at SE 82nd AvenueSpringwater Corridor$42,0003% of $1.4 millionSDCs
A replacement staff trailer for Urban Forestry$13,5003% of $450,000Major maintenance and operating
A trailer and supervisor offices at Mt. Tabor Yard$9,7503% of $325,000Major maintenance
A trail at Bridgeton SloughBridgeton Slough Natural Area$6,9003% of $230,000SDCs
FY 2029–30$7,764,367
The North Portland indoor pool$6,407,0003% of $116.9 million, plus $2.9 million to run itSDCs
Gym improvements at Multnomah Arts CenterMultnomah Arts Center$28,5003% of $950,000SDCs
Broadway Corridor Park, a new 2-acre open space between NW Hoyt and NW Johnson streets$342,0003% of $11.4 millionSDCs
A playground at Midland ParkMidland Park$75,0003% of $2.5 millionSDCs
A master plan, trails and access at Kelly Butte Natural AreaKelly Butte Natural Area$60,0003% of $2 millionSDCs
A master plan, access, habitat and trail work in Buttes Natural AreaButtes Natural Area$39,0003% of $1.3 millionSDCs
Lights for the synthetic turf field at Lents ParkLents Park$22,5003% of $750,000SDCs
The Marine Drive Trail from I-205 to NE 122nd Avenue$97,3673% of $3.2 millionMetro
Park and waterfront trail improvements in the OMSI district$120,0003% of $4 millionSDCs
Renovating the Bristlecone Pine Trail and its parking at Hoyt ArboretumHoyt Arboretum$15,0003% of $500,000SDCs
Old Town Skatepark, a covered 35,000-square-foot skatepark and plaza$450,0003% of $15 millionSDCs
New amenities at Columbia Park, to be chosen with the public (also listed under FY 2027–28)Columbia Park$54,0003% of $1.8 millionSDCs
New amenities at University Park, to be chosen with the publicUniversity Park$54,0003% of $1.8 millionSDCs
Total, as the workbook adds it$9,544,824

Metro is regional money, including Metro's 2019 parks and nature bond. Major maintenance is PP&R's repair funding. Project descriptions are the Atlas's; the workbook's own project names and numbers are in the CSV.

This year's budget entry

What PP&R entered for 2025–26: $588,917 a year

When an addition opens or land is bought, PP&R asks for its upkeep in that year's budget. The workbook lists 7 additions whose upkeep was to be built into the bureau's base budget for FY 2025–26, and the amount assigned to each division: $286,750 to Assets and Development, $216,307 to Land Stewardship, $78,433 to Recreation, and $7,427 to Urban Forestry. PP&R says every item on this list was incorporated into the budget (information provided to the Atlas, November 2026). The Atlas has not matched the lines to the adopted budget itself.

New yearly operating and maintenance money PP&R entered for its fiscal year 2025–26 base budget, by addition
AdditionUpkeep a yearHow the figure was set
The expanded part of Mt. Scott Community Center (the list counts upkeep for the added space only)Mt Scott Park$367,315PP&R's estimate for the site
The Morrison Bridgehead addition to Waterfront Park, a 66,725-square-foot plaza area under the bridgeGov Tom McCall Waterfront Park$95,926PP&R's estimate for the site
5.2 acres of donated land on SW Patton Road, which PP&R's list places next to Hoyt ArboretumHoyt Arboretum$64,7795.202 acres at $12,453
3.31 acres added to Buttes Natural Area on SE Clatsop StreetButtes Natural Area$41,2213.31 acres at $12,453
Land bought at SE 82nd Avenue on the Springwater CorridorSpringwater Corridor$13,699PP&R's estimate for the site
0.37 acres added to Baltimore Woods Natural AreaBaltimore Woods Natural Area$4,6080.37 acres at $12,453
0.11 acres added to Marquam Nature Park on SW Gaines StreetMarquam Nature Park$1,3690.11 acres at $12,453

What would settle it

Records that would turn the forecast into a plan

  • A detailed estimate for each placeholderThe worksheet PP&R's workbook says is still needed for 32 projects, with the date each was done.
  • The funding plan for each projectCity financial policy FIN 2.03 calls for a plan to pay for a new asset's upkeep, major maintenance and replacement in the adopted budget.
  • The budget lines for 2025–26PP&R says all 7 additions were incorporated into the budget. The lines themselves would show whether each got the full $588,917 entered.
  • The pool's business planWhat the $6.4 million covers, and how much of it admission and program fees are expected to pay.
  • Why a natural-area acre is priced like turfWhat the new rate pays for, and whether it applies to the natural areas PP&R already owns.
  • A current listThe same workbook for the FY 2026–27 budget, showing what opened, what moved and what was added.
  • Whether the repeated line is one project or twoThe project number and amount are the same in both years.

Sources, republished unchanged: PP&R's O&M workbook for FY 2025–26 (Audit Services work paper D-02-01-00a) and PP&R's March 2025 response to the auditors (work paper D-02-01-00). The workbooks name City staff as contacts; the Atlas's data leaves those columns out. About these work papers.