Funds and their limits
Which money can pay for what
Each source of parks money has rules about what it can buy. Here is what each one may and may not pay for, and why cancelling one project does not fund another.
Jump to · The short version
- The short version
- Why cancelling a project does not free the money
- Development charges: new capacity only
- The Parks Levy: operations, with a small share for repairs
- The General Fund: the only money with no strings
- Bonds: repairs and construction, never operations
- Regional and district money
- Golf and the Raceway
- What can pay for repairs today
- Strings that stay with the land
- What this page does not settle
- The short version
- Why cancelling a project does not free the money
- Development charges: new capacity only
- The Parks Levy: operations, with a small share for repairs
- The General Fund: the only money with no strings
- Bonds: repairs and construction, never operations
- Regional and district money
- Golf and the Raceway
- What can pay for repairs today
- Strings that stay with the land
- What this page does not settle
Money for Portland's parks sits in separate funds, and each fund has rules about what it can buy. Cancelling a project paid from one fund does not free that money for something else. The clearest case is the fee charged on new construction, called a system development charge. State law lets it build new capacity and forbids spending it on maintenance. Portland Parks & Recreation (PP&R) held $114 million of it in June 2026, while the fund that pays for major repairs is a fraction of that size. Reviewed November 16, 2026.
The short version
Each row is one source of money. "Limited" means the source can pay for part of that kind of work, under the condition given below the table.
| Source | Build something new | Major repair of what exists | Routine maintenance | Programs and staff |
|---|---|---|---|---|
| Development charges (SDCs) | Yes | Limited | No | No |
| 2025 Parks Levy | No | Limited | Yes | Yes |
| General Fund | Yes | Yes | Yes | Yes |
| Voter-approved bonds | Yes, if the ballot says so | Yes | No | No |
| Metro bond local share | Limited | Yes | No | No |
| Tax increment (urban renewal) | Yes, inside the district | Yes, inside the district | No | No |
| Local improvement district | Yes, the named project | Yes, the named project | No | No |
| Golf and Raceway funds | Golf and raceway | Golf and raceway | Golf and raceway | Limited |
The General Fund is the only source that can pay for everything, and it is the one every other City service competes for.
Why cancelling a project does not free the money
The North Portland Aquatic Center is the example people reach for. PP&R lists $91.5 million secured for it: $76.5 million in development charges, set aside in three steps between April 2021 and December 2023, and $15 million in state lottery funds. Development charges are 84 percent of the total. PP&R project page · PP&R questions and answers, February 2025
If the City cancelled the pool tomorrow, the $76.5 million would go back into the development charge fund. It could then pay for a different project that adds capacity: a new park, a larger playground, a new trail. It could not replace a failing roof, fix a restroom or pay a maintenance worker. PP&R's own answer on the pool says development charges cannot pay for "repairing a failed building."
So the real trade-off inside that fund is between one new thing and another new thing. The trade-off with repairs happens somewhere else: in what each new thing costs to run and maintain once it opens, because that bill lands on the General Fund and the levy. In October 2025 the City Auditor found that PP&R had approved projects without a plan to pay for their upkeep. Five of the eight projects it sampled carried estimates adding up to about $4.7 million a year. City Auditor, October 2025 · Upkeep of new parks
Development charges: new capacity only
A system development charge (SDC) is a one-time fee a builder pays when new construction adds demand on parks. Oregon law says the money "may be spent only on capacity increasing capital improvements" and may not pay for operating or maintaining what it builds. Portland's code repeats the ban on maintenance and repair. ORS 223.307 · Portland City Code 17.13
Can it fix an existing building at all? Only the share of a project that adds capacity. This is why PP&R gives every item on its repair list a "Growth %." Of the 1,814 open items on the list in October 2026, 1,236 are marked 0 percent growth, so development charges cannot touch them. Another 492 are marked 100 percent and 86 are in between. Largest items on the repair list
How much is there? The fund held $113.97 million at the end of fiscal year 2025-26. That year it took in $2.61 million in fees and $4.85 million in interest, and spent $12.95 million. Parks SDC annual report, 2025-26
Is more coming? Less than before. The City Council exempted new housing from these fees for permits issued between August 15, 2025 and September 30, 2028. Ordinance 192082
The imbalance shows in PP&R's five-year capital plan. Of $201.0 million, $152.4 million is for growth and $23.1 million is for major maintenance. FY 2026-27 Adopted Budget, Volume 2
The General Fund: the only money with no strings
The General Fund is the City's main account, filled by property and business taxes and divided among all bureaus by the Council each year. PP&R's General Fund budget for fiscal year 2026-27 is $173.3 million. Most of that is levy money and fees passing through. The discretionary part, which the Council could move to any purpose, is $67.4 million. FY 2026-27 Adopted Budget, Volume 2
It can pay for repairs, and it has: PP&R reports about $5 million a year for major maintenance in fiscal year 2023-24. Every dollar moved to repairs comes out of something else the Council funds. PP&R funding sources
Bonds: repairs and construction, never operations
A general obligation bond is borrowing that voters approve and repay through property taxes. The Oregon Constitution limits it to capital costs, meaning land and things that last more than a year, and excludes routine maintenance and supplies. Oregon Constitution, Article XI, section 11L
Portland's last parks bond was the $68 million Parks Replacement Bond of 2014, for urgent repairs and replacements. PP&R says it is nearly complete and has no money left for further projects. A bond is the one tool sized for a large repair list, and there is none in place today. Parks Replacement Bond · PP&R funding sources
Regional and district money
Metro's 2019 parks and nature bond gave local park agencies a share to spend on their own projects. The Portland City Council approved a slate of projects for the City's share in May 2022, and PP&R's five-year capital plan carries $20.5 million of it. It pays for significant repairs and some improvements at existing sites, and it cannot pay for programs or staff. In April 2026 Metro approved $2.75 million of it for trail bridges. PP&R Local Share page · Metro, April 2026
Tax increment financing sets aside the growth in property taxes inside a district to pay for projects named in that district's plan. It is capital money and it stays in the district. ORS 457.170
A local improvement district lets property owners agree to be assessed for a specific improvement near them. The parks example is the restoration of the Portland Open Space Sequence, the chain of downtown fountains and plazas designed by Lawrence Halprin. The Council formed the district in December 2016, owners assessed themselves $2.15 million, the City added its own share, and the work was finished in July 2019. PP&R, July 2019 · City Code 17.08
Golf and the Raceway
Golf courses and Portland International Raceway each have their own fund, filled by what their customers pay. By City policy golf revenue goes to the Golf Fund. The policy does not forbid moving money out, and in May 2025 the Council moved $1.825 million from the Golf Fund to other uses, including $1 million for parks. City policy FIN-3.54 · Willamette Week, May 27, 2025
What can pay for repairs today
Putting the rows together, a repair to an existing park or building has four possible payers:
- The General Fund, in competition with every other City service.
- The levy's capital share, about $2 million a year.
- Metro's local share, a fixed sum that is already assigned to projects.
- A new bond, which voters would have to approve.
Grants and gifts can help where their terms allow. Development charges, the largest pile of capital money PP&R holds, are not on the list.
Strings that stay with the land
Money has rules when it is spent. Some of it also leaves rules behind, on the land or building it paid for, and those rules outlast the grant.
Land and Water Conservation Fund grants. A park bought or improved with one of these federal grants gets a mapped "6(f)" boundary. Inside it the land has to stay public outdoor recreation land. It can be converted to another use only if the National Park Service approves and the owner substitutes land of at least equal market value and reasonably equal usefulness. The rule applies whether the grant bought the land or only improved it. National Park Service: LWCF protection
Oregon State Parks keeps a public map of every 6(f) boundary in the state. As of November 2026 its boundaries fall on 39 PP&R properties: Arbor Lodge Park, Argay Park, Brooklyn School Park, Cathedral Park, Darcelle XV Plaza, Dr Martin Luther King Jr School Park, East Delta Park, Eastmoreland Golf Course, Ed Benedict Park, Fernhill Park, Forest Park, Glenwood Park, Gov Tom McCall Waterfront Park, Hazelwood Community Garden, Irving Park, John Luby Park, Kelley Point Park, Knott Park, Leach Botanical Garden, Marquam Nature Park, Midland Park, Mill Park, Northgate Park, Oaks Bottom Wildlife Refuge, Pendleton Park, Pier Park, Pioneer Courthouse Square, Powell Butte Nature Park, Raymond Park, Sacajawea Park, Sellwood Riverfront Park, South Waterfront Park, Thomas Cully Property, Ventura Park, Verdell Burdine Rutherford Park, West Powellhurst Park, Wilkes Park, Willamette Moorage, Willamette Park. A boundary does not always follow the park's edge. By the Atlas's measure it takes in nearly all of the property at 25 of the 39, most of it at seven, and less than half at seven. Forest Park is ringed almost entirely. At Eastmoreland Golf Course the boundary takes in only a sliver. The state's map shows where each one runs. The state also maps boundaries along the Eastbank Esplanade, the Marine Drive Trail and the Terwilliger bike path that the Atlas could not match to a property outline. Oregon State Parks: LWCF map
Urban Park and Recreation Recovery grants. This federal program paid to rehabilitate city recreation sites between 1978 and 2002. A site rehabilitated with its money stays protected for public recreation in perpetuity under Section 1010 of the program's law, and converting it to another use needs the National Park Service's approval. National Park Service: UPARR
The Atlas has confirmed two Portland sites from records of the time. The Interstate Firehouse Cultural Center was converted from an abandoned firehouse with a $420,000 grant, matched by $180,000 from the City. The community center in University Park, now the Charles Jordan Community Center, received two grants for its renovation, $500,000 and later $525,000. There is no public list of every Portland site, so there may be more. The Park Service says the obligation covers the whole area drawn in each project's documents, whatever share of the work the grant paid for. The Atlas has not seen those documents, so it cannot say which parcels at either site are covered. Portland Observer, August 11, 1982 · PP&R newsletter, May 2006 · National Park Service: UPARR questions
Easements. PP&R holds easements across other owners' land, many of them for trails, and grants easements across park land to others, often for utilities. PP&R publishes a map of them. PP&R easement map
What this means for a budget: a protected park cannot be sold or turned to another use to raise money or cut costs without replacing it, so these parks are a fixed part of what the system has to keep up.
What this page does not settle
- The pool's running cost. PP&R has not published what the North Portland Aquatic Center will cost to operate each year or which fund will pay.
- The pool's total cost. PP&R's page gives $91.5 million secured. Other City documents the Atlas holds show higher project totals.
- Fees lost to the housing exemption. Published estimates of the development charges PP&R will forgo differ, and the Atlas has not found a City figure it can confirm.
- Other strings on park land. Deeds, bond terms, Metro agreements, flood-buyout grants and historic listings can each limit what a park may become. The Atlas has not collected them park by park.
- Tax increment rules. The statute ties spending to a district's plan. The Atlas has not read each Portland district's plan for what it allows in parks.
This page summarizes the rules. It is not legal advice, and a project's eligibility depends on its details. If something here is wrong, the corrections page is the place to say so.