Renovate 1 soccer and 2 ball fields$8,342,574
Asset as named in source: Columbia Park
PP&R sports fields are in varying conditions. Significant improvements have been made but a few still need irrigation and improved goals, etc.
KGW table row 129. Source field: “Escalated Estimate.” Estimate date, inflation basis, funded amount and completion status are not supplied.
Original source table ↗Pool and Building Demolition$765,001
Asset as named in source: Indoor pool
Demolish indoor pool buidling. If approved by Commissioner-in-Charge: Demolish At-Risk Building (based on third-party analysis), Reinvest OpEx elsewhere.
KGW table row 131. Source field: “Escalated Estimate.” Estimate date, inflation basis, funded amount and completion status are not supplied.
Original source table ↗ESPC-II_ Columbia Park$569,288
Asset as named in source: Not specified
Develop new well at Columbia Park for irrigation purposes. Install new submersible well pump estimated as 60HP with 300gpm at 156'.. FIM Name: 18.04-0017 Develop New Well
KGW table row 135. Source field: “Escalated Estimate.” Estimate date, inflation basis, funded amount and completion status are not supplied.
Original source table ↗Renovate tennis court$560,018
Asset as named in source: Sport court 2
Renovate tennis courts rated 4 or 5 in sport court assessment
KGW table row 136. Source field: “Escalated Estimate.” Estimate date, inflation basis, funded amount and completion status are not supplied.
Original source table ↗Restroom Renovation$294,012
Asset as named in source: Columbia Park Annex
Restroom A: Repair / replace roof , fixtures, lighting, access
KGW table row 141. Source field: “Escalated Estimate.” Estimate date, inflation basis, funded amount and completion status are not supplied.
Original source table ↗Columbia Cottage HVAC and Roof$216,472
Asset as named in source: Columbia Cottage
- Replace failing furnace. System is at end of life.
- Replace the roof as it is in the end of life cycle. Roof condition was detremind through building assessment
KGW table row 142. Source field: “Escalated Estimate.” Estimate date, inflation basis, funded amount and completion status are not supplied.
Original source table ↗ESPC-II_ Columbia Park Annex$125,609
Asset as named in source: Not specified
Interconnect the water service at Columbia Park Annex with the new well system at the adjacent Columbia Park property.. FIM Name: 18.06-1104 Interconnect Irrigation to Adjacent Property Well System
KGW table row 143. Source field: “Escalated Estimate.” Estimate date, inflation basis, funded amount and completion status are not supplied.
Original source table ↗Restore handball court$54,191
Asset as named in source: Court
Handball court is deteriorating and rated as 5 in court assessmet. The whole court need to remove or restore.
KGW table row 137. Source field: “Escalated Estimate.” Estimate date, inflation basis, funded amount and completion status are not supplied.
Original source table ↗ESPC-II_ Columbia Park$45,956
Asset as named in source: Not specified
Columbia Park - Retro commission all irrigation sprinkler systems and heads to ensure proper thrown and timing. Replace 10% of all rotary and spray heads.. FIM Name: 18.10-0017 Irrigation System Improvements
KGW table row 139. Source field: “Escalated Estimate.” Estimate date, inflation basis, funded amount and completion status are not supplied.
Original source table ↗Pathway Renovation$33,827
Asset as named in source: Columbia Park
Replace the damaged pathway, trails and sidewalks that have been rated as 5 in Pathway assessment
KGW table row 140. Source field: “Escalated Estimate.” Estimate date, inflation basis, funded amount and completion status are not supplied.
Original source table ↗Front doors ADA compliance$11,760
Asset as named in source: Columbia Pool
The front doors are not ADA compliant. There is no push button to automatically open the door. We have been getting complaints from our customers in wheelchairs and those using walkers.
KGW table row 144. Source field: “Escalated Estimate.” Estimate date, inflation basis, funded amount and completion status are not supplied.
Original source table ↗Replace Backflow preventer device$10,000
Asset as named in source: Property
- Replace out of compliance backflow preventer
- Assembly: Double Check Valve Assembly (DCVA)
- Premises Isolation (PI): 1" Double Check (DC)+ Vault. Serial # 01970
- Move to property line, if needed
- Hazard: Right Of Way (ROW)
KGW table row 145. Source field: “Escalated Estimate.” Estimate date, inflation basis, funded amount and completion status are not supplied.
Original source table ↗ESPC-II_ Columbia Park$8,139
Asset as named in source: Not specified
Replace (1) existing Waterplay Monster ground spray (32 gpm @ 5ft) with wave nozzle (6 gpm) and replace (1) existing Waterplay Cosmic Cannon (6 gpm) to Solor Spurt (1.5 gpm).. FIM Name: 18.08-0017 Splash Pad Water Use Reduction
KGW table row 130. Source field: “Escalated Estimate.” Estimate date, inflation basis, funded amount and completion status are not supplied.
Original source table ↗ESPC-II_ Columbia Park$7,040
Asset as named in source: Not specified
Convert existing lighting to LED technology via a re-lamp approach.. FIM Name: 09.06-0017 Building Interior Lighting LED Conversion
KGW table row 134. Source field: “Escalated Estimate.” Estimate date, inflation basis, funded amount and completion status are not supplied.
Original source table ↗ESPC-II_ Columbia Park Annex$5,745
Asset as named in source: Not specified
Columbia Park Annex - Retro commission all irrigation sprinkler systems and heads to ensure proper thrown and timing. Replace 10% of all rotary and spray heads.. FIM Name: 18.10-1104 Irrigation System Improvements
KGW table row 138. Source field: “Escalated Estimate.” Estimate date, inflation basis, funded amount and completion status are not supplied.
Original source table ↗ESPC-II_ Columbia Park$826
Asset as named in source: Not specified
Convert existing lighting to LED technology via a re-lamp approach.. FIM Name: 09.07-0017 Building Exterior Lighting LED Conversion
KGW table row 128. Source field: “Escalated Estimate.” Estimate date, inflation basis, funded amount and completion status are not supplied.
Original source table ↗ESPC-II_ Columbia Park Annex$760
Asset as named in source: Not specified
Convert existing lighting to LED technology via a re-lamp approach.. FIM Name: 09.06-1104 Building Interior Lighting LED Conversion
KGW table row 132. Source field: “Escalated Estimate.” Estimate date, inflation basis, funded amount and completion status are not supplied.
Original source table ↗ESPC-II_ Columbia Park Annex$733
Asset as named in source: Not specified
Install a GE control node on each pathway light fixture. Node for parks with <50 fixtures will be model #ELWM18BXXXXAD. Node for parks with >50 fixtures will be model #ELWN08BXXXXAD.. FIM Name: 09.17-1104 Building Exterior Lighting Controls
KGW table row 133. Source field: “Escalated Estimate.” Estimate date, inflation basis, funded amount and completion status are not supplied.
Original source table ↗ESPC-II_ Columbia Park Annex$99
Asset as named in source: Not specified
Convert existing lighting to LED technology via a re-lamp approach.. FIM Name: 09.07-1104 Building Exterior Lighting LED Conversion
KGW table row 127. Source field: “Escalated Estimate.” Estimate date, inflation basis, funded amount and completion status are not supplied.