Portland Parks & Recreation has 1,814 repairs and replacements on its open backlog. This page lists them top to bottom in the bureau's own priority order, with the reasons PP&R recorded for each, and shows what the backlog is made of: where the money is and what kind of work it is. It shows what the bureau rates most urgent. It cannot yet show what will be fixed next, because the funded list, current costs and the rule for breaking ties are not public.
PP&R's backlog projects map workbook, extract dated 2026-10-12. Scores are the bureau's, unchanged. Capital budgets are from the FY 2026–27 adopted budget.
Read this first
Why the top of this list is not yet a spending plan
- Most items share a score.1,510 items have a score above zero, but there are only 33 different scores among them. 11 items tie at the top score of 100, and 60 score 75 or higher. PP&R publishes no rule for ordering items with the same score, so the list below lets you choose one and says which is in use.
- Cost is not part of the score.40 of the 60 items scored 75 or higher match a November 2023 estimate, $11M together. The other 20 have no published cost. Among the items tied at 100, the 2023 estimates run from $30,000 (renovate retaining wall, Kelly Butte Natural Area) to $739,490 (building renovation, Maint Facility - SE 136th and Holgate).
- How many people use a place is not part of the score.5 of the 11 items tied at the top are at a staff maintenance yard or a fee-supported golf or racing site. The score weighs an asset's risk of failing and the neighborhood around it.
- Funding status is not public.13 of the 31 places with an item scored 75 or higher have any money in this year's adopted capital budget, and that money may be for other work at the site. Another $69.4M of the capital budget could not be tied to any site, much of it citywide programs and new parks, so a park with no line here may still be getting work.
- Waiting time is not part of the score.The oldest item scored 75 or higher, “Replace Elephant Barn Roof” at Washington Park, was requested in FY 09/10, 17 years ago.
What the backlog is made of
17 projects hold half the cost
PP&R's backlog workbook lists 1,814 open items. 941 of them match a November 2023 cost estimate, and those estimates add up to $506.2M. The other 873 have no published cost, so that total is not the size of the backlog. PP&R's own headline, about $759M, counts with a different scope and date, and the two can't be matched item by item.
A few large projects, many small ones
The 17 largest items account for $257M, half of the priced total, and the ten largest alone for 39%. PP&R marks 13 of those 17 as partly adding capacity, not only repairing what exists. At the other end, half of all priced items cost $70.1K or less, and together they come to $11.8M, 2.3% of the total. The cheapest 85%, 800 items of $470.4K or less each, add up to $75M.
| 2023 estimate | Items | Share of items | Dollars | Share of dollars |
|---|---|---|---|---|
| Under $100,000 | 53557% | $17.1M3.4% | ||
| $100,000 to $1 million | 33335% | $102.9M20% | ||
| $1 million to $10 million | 646.8% | $195.9M39% | ||
| $10 million or more | 9under 1% | $190.2M38% |
What kind of work it is
Master plans, expansions and redevelopment is the largest type by cost: 46 items and $140.9M, 28% of the priced total, though only 16 of the 46 carry a price. The most numerous types are small jobs. 239 energy-efficiency retrofits, many of them LED lighting, come to $7.2M, and 214 path, trail and stair items come to $39.3M.
| Type of work | Items | With a price | 2023 estimates | Share of dollars | Typical item |
|---|---|---|---|---|---|
| Buildings | $152.3M | 30% of dollars | |||
| Community centers and other buildings | 84 | 38 | $92.5M | $145.2K | |
| Seismic and structural | 30 | 20 | $19.3M | $188.9K | |
| Staff workspaces | 76 | 25 | $15M | $30K | |
| Heating, plumbing and other building systems | 61 | 33 | $14.6M | $81.7K | |
| Roofs | 73 | 28 | $10.9M | $112.7K | |
| Recreation facilities | $106.5M | 21% of dollars | |||
| Sports fields and courts | 147 | 100 | $87.2M | $221.7K | |
| Playgrounds | 78 | 53 | $14.1M | $206K | |
| Pools and splash pads | 40 | 12 | $4.4M | $116.3K | |
| Restrooms | 22 | 7 | $733.6K | $65.3K | |
| Paths, parking and bridges | $74.2M | 15% of dollars | |||
| Paths, trails and stairs | 214 | 164 | $39.3M | $75.2K | |
| Parking lots and roads | 89 | 53 | $27.6M | $209.3K | |
| Bridges, docks and boardwalks | 41 | 14 | $6.9M | $273.2K | |
| Accessible routes (ADA) | 169 | 4 | $502.5K | $85.9K | |
| Grounds, water and energy | $31.8M | 6.3% of dollars | |||
| Natural areas and trees | 83 | 66 | $12.3M | $147K | |
| Energy-efficiency retrofits | 239 | 197 | $7.2M | $11.8K | |
| Walls, fences, plazas and other site features | 76 | 37 | $6.2M | $60K | |
| Site lighting and electrical | 37 | 21 | $3.1M | $58.1K | |
| Irrigation, water and drainage | 82 | 51 | $2.9M | $10K | |
| Expansions and new parks | $140.9M | 28% of dollars | |||
| Master plans, expansions and redevelopment | 46 | 16 | $140.9M | $7.6M | |
| New parks and unnamed future projects | 122 | 1 | $12.8K | $12.8K | |
| Other | $492.2K | under 1% of dollars | |||
| Other or unclear | 5 | 1 | $492.2K | $492.2K | |
Each item has one type. The Atlas reads it from PP&R's title, then the description, using keyword rules and a hand-checked list for the largest mixed projects, so a whole-building renovation counts as a building even when it includes a new roof. It is a reading, not a City field. Select a type to see its items below; the type is also a column in the spreadsheet, so you can check or regroup it.
Repair or added capacity, by PP&R's own measure
PP&R gives every item a growth percentage: the share of the project that adds capacity for a growing city, the part that System Development Charges on new construction can pay for. The 86 items it marks 50% growth hold $256.3M, 51% of the priced total. None of the 492 items marked 100% growth has a 2023 estimate. Taking PP&R's percentages at face value, about $128.2M of the $506.2M is growth rather than repair.
No growth: repair and replacement
1,236 items · 857 priced · $249.9M
50% growth
86 items · 84 priced · $256.3M
100% growth
492 items · 0 priced · no estimates
What the most urgent items would cost
The items PP&R scores highest are mostly small jobs. The 343 items scored 48 or higher come to $56.3M for the 228 that have a price, 11% of the priced total. Items scored 24 to 47 hold 51% of the dollars.
Top · 75 and above
60 items · 40 priced · $11M
High · 48 to 74
283 items · 188 priced · $45.3M
Medium · 24 to 47
822 items · 523 priced · $259.4M
Lower · 1 to 23
345 items · 141 priced · $104M
Unscored · no score, or a score of 0
304 items · 49 priced · $86.5M
The same job, park by park
PP&R lists many identical jobs separately at each place. Its public records don't say whether they are designed and bid together or one park at a time, which can change what they cost. These titles each appear at ten or more places.
| PP&R's title | Places | With a price | 2023 estimates | Typical item |
|---|---|---|---|---|
| Provide ADA compliance accessible path of travel | 160 | 0 | — | — |
| Pathway Renovation | 135 | 134 | $29.7M | $77.4K |
| ESPC-III_Buildings Lighting to LEDs | 70 | 48 | $564.5K | $11.8K |
| Playground renovation | 38 | 37 | $9.3M | $205.8K |
| Replace Backflow preventer device | 38 | 37 | $482K | $10K |
| ESPC-III_Pathway Lighting to LEDs | 29 | 29 | $1.3M | $21.2K |
| Renovate parking lot_Parking Area A | 18 | 18 | $9M | $258.2K |
| Renovate parking lot area | 18 | 0 | — | — |
| Renovate sport field | 17 | 16 | $14.2M | $714.2K |
| Replace old HVAC system | 17 | 13 | $11.3M | $113.1K |
How to read these numbers
- Costs are November 2023 planning estimates published by KGW, matched to today's items only where the title and description match at the same place. They are not bids or current prices.
- 873 items have no estimate, including every item PP&R marks 100% growth and nearly every accessible-route item, so every total here leaves them out.
- Scores and growth percentages are PP&R's own. The type of work is the Atlas's reading of PP&R's words.
The list
Every open item, in PP&R's order
Score 100 · 11 items, tied
PP&R publishes no order for items with the same score. Listed here oldest request first. 2023 estimates for 9 of 11: $2.1M.
- #1100Top$724.9K2023 estimate
Fire Protection improvement
University Park · District 2
Heating, plumbing and other building systems · Failure risk 25 of 25 · equity 4 of 5 · Staff project entry · requested FY 18/19, 8 years ago · CIP 805
FY 2026–27 capital budget at this site: $1M (University Park Amenities; CJCC HVAC Grant). It may pay for other work at the site.
What PP&R's record says
Redesign the quantity and position of sprinklers in basement area. Provide sprinkler protection in unprotected crawl spaces.
- #2100Top$90.8K2023 estimate
Renovate the Roof of Residence building
Leach Botanical Garden · District 1
Roofs · Failure risk 25 of 25 · equity 4 of 5 · Condition assessment · requested FY 19/20, 7 years ago · CIP 1729
The Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Fix or replace the Roof that is rated 4 through buildings' assessment 17-18 Project update upon condition assessment outcome 24-25
- #3100Top$122.2K2023 estimate
Renovate the Roof of Maintenance building
Portland International Raceway · District 2
Roofs · Failure risk 25 of 25 · equity 4 of 5 · Condition assessment · requested FY 19/20, 7 years ago · CIP 1751
Fee-supported site: golf or RacewayThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Fix or replace the Roof that is rated 4 through buildings' assessment 17-18 Project update upon condition assessment outcome 24-25
- #4100Top$225.1K2023 estimate
Renovate sport field
Gilbert Primary Park · District 1
Sports fields and courts · Failure risk 25 of 25 · equity 4 of 5 · Condition assessment · requested FY 22/23, 4 years ago · CIP 2012
The Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Sport fields rated 4 or 5 in condition assessment
- #5100Top$739.5K2023 estimate
Building renovation
Maint Facility - SE 136th and Holgate · District 1
Community centers and other buildings · Failure risk 25 of 25 · equity 4 of 5 · Condition assessment · requested FY 23/24, 3 years ago · CIP 4380
Staff site: maintenance yard or officeThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Renovate buildings rated 4 or 5 in condition assessment 17-18 Project update upon condition assessment outcome 24-25- need full renovation including the roof
- #6100Top$30K2023 estimate
Renovate retaining wall
Kelley Point Park · District 2
Walls, fences, plazas and other site features · Failure risk 25 of 25 · equity 4 of 5 · Condition assessment · requested FY 23/24, 3 years ago · CIP 4422
FY 2026–27 capital budget at this site: $1.5M (Kelley Point Picnic Improvements). It may pay for other work at the site.
What PP&R's record says
investigate and repair or replace retaining walls
- #7100Top$30K2023 estimate
Renovate retaining wall
Kelly Butte Natural Area · District 1
Walls, fences, plazas and other site features · Failure risk 25 of 25 · equity 4 of 5 · Condition assessment · requested FY 23/24, 3 years ago · CIP 4423
FY 2026–27 capital budget at this site: $400K (Kelly Butte Access Impr). It may pay for other work at the site.
What PP&R's record says
investigate and repair or replace retaining walls
- #8100Top$50K2023 estimate
Renovate electrical and mechanical equipment
Maint Facility - SE 136th and Holgate · District 1
Heating, plumbing and other building systems · Failure risk 25 of 25 · equity 4 of 5 · Staff project entry · requested FY 23/24, 3 years ago · CIP 4425
Staff site: maintenance yard or officeThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Electrical and mechanical equipment’s passed 25 year of service and need to replace.
- #9100Top$100K2023 estimate
Renovate electrical and mechanical equipment
Portland International Raceway · District 2
Heating, plumbing and other building systems · Failure risk 25 of 25 · equity 4 of 5 · Staff project entry · requested FY 23/24, 3 years ago · CIP 4432
Fee-supported site: golf or RacewayThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Electrical and mechanical equipment’s passed 25 year of service and need to replace.
- #10100TopNo cost
Replace or fix play surface
Ventura Park · District 1
publishedPlaygrounds · Failure risk 25 of 25 · equity 4 of 5 · Work order · requested FY 24/25, 2 years ago · CIP 4724
Levy category · playgroundThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Replace/fix paly surface (AstroTurf) at artful play equipment which is torn and frayed, causing ripping hazard. Seams around edge of rocks have become loose and are no longer attached.
- #11100TopNo cost
Carport roof replacement
Portland International Raceway · District 2
publishedRoofs · Failure risk 25 of 25 · equity 4 of 5 · Condition assessment · requested FY 24/25, 2 years ago · CIP 4806
Fee-supported site: golf or RacewayThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Building condition assessment 24-25: replace the roof
Score 80 · 28 items, tied
PP&R publishes no order for items with the same score. Listed here oldest request first. 2023 estimates for 22 of 28: $5.4M.
- #1280Top$199.9K2023 estimate
Roof replacement
Chimney Park · District 2
Roofs · Failure risk 20 of 25 · equity 4 of 5 · Condition assessment · requested FY 18/19, 8 years ago · CIP 1158
FY 2026–27 capital budget at this site: $4K (Columbia Blvd Bridge @ Chimney Park). It may pay for other work at the site.
What PP&R's record says
- The roof of Garage and maintenance facility is in end of life cycle - This project derived from Building assessment - Project update upon condition assessment 24-25
- #1380Top$555.6K2023 estimate
Playground renovation
University Park · District 2
Playgrounds · Failure risk 20 of 25 · equity 4 of 5 · Work order · requested FY 19/20, 7 years ago · CIP 1050
Levy category · playgroundFY 2026–27 capital budget at this site: $1M (University Park Amenities; CJCC HVAC Grant). It may pay for other work at the site.
What PP&R's record says
- The vinyl coating is coming off of the play structure platforms and is creating jagged edges, potential for a bad scrape. - Install play equipment in the soft surface area at the north end of the building, new addition, and expand play area to add more equipment (current range is inadequate). Add sizeable free play area, per Technical Paper. -Playgroun…
- #1480Top$238.8K2023 estimate
Pathway Renovation
Harney Park · District 3
Paths, trails and stairs · Failure risk 20 of 25 · equity 4 of 5 · Condition assessment · requested FY 19/20, 7 years ago · CIP 1092
FY 2026–27 capital budget at this site: $201.2K (Replace Harney Play Structure). It may pay for other work at the site.
What PP&R's record says
Pathway: - Replace the damaged pathway, trails and sidewalks that have been rated as 4 and 5 in Pathway assessment - The concrete path leading to the basketball courts near the bike lock up. Most of the pathway is in need of replacement 400’x8’wide Sidewalk: - Report from PDX Reporter that there is a hazardous raised/sunken sidewalk just north of the socc…
- #1580Top$645.3K2023 estimate
Pathway Renovation
Kelley Point Park · District 2
Paths, trails and stairs · Failure risk 20 of 25 · equity 4 of 5 · Condition assessment · requested FY 19/20, 7 years ago · CIP 1099
FY 2026–27 capital budget at this site: $1.5M (Kelley Point Picnic Improvements). It may pay for other work at the site.
What PP&R's record says
Replace the damaged pathway, trails and sidewalks that have been rated as 4 and 5 in Pathway assessment
- #1680Top$28.8K2023 estimate
Pathway Renovation
Leach Botanical Garden · District 1
Paths, trails and stairs · Failure risk 20 of 25 · equity 4 of 5 · Condition assessment · requested FY 19/20, 7 years ago · CIP 1123
The Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Replace the damaged pathway, trails and sidewalks that have been rated as 4 and 5 in Pathway assessment
- #1780Top$76.4K2023 estimate
Pathway Renovation
Stark Street Island · District 1
Paths, trails and stairs · Failure risk 20 of 25 · equity 4 of 5 · Condition assessment · requested FY 19/20, 7 years ago · CIP 1143
The Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Replace the damaged pathway, trails and sidewalks that have been rated as 4 and 5 in Pathway assessment
- #1880Top$6.2K2023 estimate
ESPC-II_ Maint Facility - SE 136th and Holgate
Maint Facility - SE 136th and Holgate · District 1
Energy-efficiency retrofits · Failure risk 20 of 25 · equity 4 of 5 · Staff project entry · requested FY 19/20, 7 years ago · CIP 1336
Staff site: maintenance yard or officeThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Add R-38 fiberglass batt insulation to underside of roof deck in shop area.. FIM Name: 13.02-0675 Add Roof Insulation
- #1980Top$21.2K2023 estimate
ESPC-II_ Charles Jordan Community Center
University Park · District 2
Energy-efficiency retrofits · Failure risk 20 of 25 · equity 4 of 5 · Staff project entry · requested FY 19/20, 7 years ago · CIP 1342
FY 2026–27 capital budget at this site: $1M (University Park Amenities; CJCC HVAC Grant). It may pay for other work at the site.
What PP&R's record says
CJCC; Install 100 occupancy sensor plug load power strips throughout the facility to reduce plug load power consumption for loads that do not need to be on 24/7 such as computer monitors, TVs, scanners, paper shredders, printers, speakers, etc. All CPUs, modems, and routers to be plugged into "always on" ports in power strip to ensure connectivity for the…
- #2080Top$1.1K2023 estimate
ESPC-II_ East Portland Community Center & Pool
Floyd Light Park · District 1
Energy-efficiency retrofits · Failure risk 20 of 25 · equity 4 of 5 · Staff project entry · requested FY 19/20, 7 years ago · CIP 1415
FY 2026–27 capital budget at this site: $90K (EPCC Roof Repair). It may pay for other work at the site.
What PP&R's record says
EPCC - Retro commission all irrigation sprinkler systems and heads to ensure proper thrown and timing. Replace 10% of all rotary and spray heads.. FIM Name: 18.10-0104 Irrigation System Improvements
- #2180Top$11.8K2023 estimate
ESPC-III_Buildings Lighting to LEDs
Floyd Light Park · District 1
Energy-efficiency retrofits · Failure risk 20 of 25 · equity 4 of 5 · Staff project entry · requested FY 19/20, 7 years ago · CIP 1458
FY 2026–27 capital budget at this site: $90K (EPCC Roof Repair). It may pay for other work at the site.
What PP&R's record says
LED conversion for Exterior and Interior Lights
- #2280TopNo cost
ESPC-III_Buildings Lighting to LEDs
University Park · District 2
publishedEnergy-efficiency retrofits · Failure risk 20 of 25 · equity 4 of 5 · Staff project entry · requested FY 19/20, 7 years ago · CIP 1505
FY 2026–27 capital budget at this site: $1M (University Park Amenities; CJCC HVAC Grant). It may pay for other work at the site.
What PP&R's record says
LED conversion for Exterior and Interior Lights
- #2380Top$360.4K2023 estimate
Renovate the Roof of Administration building
Portland International Raceway · District 2
Roofs · Failure risk 20 of 25 · equity 4 of 5 · Condition assessment · requested FY 19/20, 7 years ago · CIP 1735
Fee-supported site: golf or RacewayThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Fix or replace the Roof that is rated 4 through buildings' assessment 17-18 Project update upon condition assessment outcome 24-25
- #2480Top$103.1K2023 estimate
Renovate the Roof of Shelter - Restroom building
Kelley Point Park · District 2
Roofs · Failure risk 20 of 25 · equity 4 of 5 · Condition assessment · requested FY 19/20, 7 years ago · CIP 1760
Levy category · restroomFY 2026–27 capital budget at this site: $1.5M (Kelley Point Picnic Improvements). It may pay for other work at the site.
What PP&R's record says
Fix or replace the Roof that is rated 4 through buildings' assessment Project update upon condition assessment outcome 24-25
- #2580Top$80.4K2023 estimate
Renovate the Roof of Restroom - Storage building
University Park · District 2
Roofs · Failure risk 20 of 25 · equity 4 of 5 · Condition assessment · requested FY 19/20, 7 years ago · CIP 1761
Levy category · restroomFY 2026–27 capital budget at this site: $1M (University Park Amenities; CJCC HVAC Grant). It may pay for other work at the site.
What PP&R's record says
Fix or replace the Roof that is rated 4 through buildings' assessment 17-18 Project update upon condition assessment outcome 24-25.
- #2680Top$33.4K2023 estimate
Renovate the Roof of Visitor Services building
Portland International Raceway · District 2
Roofs · Failure risk 20 of 25 · equity 4 of 5 · Condition assessment · requested FY 19/20, 7 years ago · CIP 1783
Fee-supported site: golf or RacewayThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Fix or replace the Roof that is rated 4 through buildings' assessment Project update upon condition assessment outcome 24-25
- #2780Top$235.2K2023 estimate
Pathway Renovation
Portland International Raceway · District 2
Paths, trails and stairs · Failure risk 20 of 25 · equity 4 of 5 · Condition assessment · requested FY 19/20, 7 years ago · CIP 4433
Fee-supported site: golf or RacewayThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Replace the damaged pathway, trails and sidewalks that have been rated as 4 and 5 in Pathway assessment
- #2880Top$209.3K2023 estimate
Renovate parking lot_Parking Area A
University Park · District 2
Parking lots and roads · Failure risk 20 of 25 · equity 4 of 5 · Condition assessment · requested FY 20/21, 6 years ago · CIP 1637
FY 2026–27 capital budget at this site: $1M (University Park Amenities; CJCC HVAC Grant). It may pay for other work at the site.
What PP&R's record says
Repair parking lot that was rated 4 in condition assessment. Repair include surface, drainage and curb. approx area= 12801 sq.ft Project update upon condition assessment outcome 24-25
- #2980Top$328K2023 estimate
Playground renovation
Hancock Park · District 3
Playgrounds · Failure risk 20 of 25 · equity 4 of 5 · Condition assessment · requested FY 20/21, 6 years ago · CIP 1874
At risk of closure · playgroundLevy category · playgroundThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
- Renovation or repair playground that was rated as 4 during playground assessment in 2020 - Potentially joining Metro Bond Local Share Pathways Work.
- #3080Top$177K2023 estimate
Playground renovation
Argay Park · District 1
Playgrounds · Failure risk 20 of 25 · equity 4 of 5 · Condition assessment · requested FY 20/21, 6 years ago · CIP 1875
At risk of closure · playgroundLevy category · playgroundThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Renovation or repair playground that was rated as 4 during playground assessment in 2020
- #3180Top$165.7K2023 estimate
Playground renovation
University Park · District 2
Playgrounds · Failure risk 20 of 25 · equity 4 of 5 · Condition assessment · requested FY 20/21, 6 years ago · CIP 1891
Levy category · playgroundFY 2026–27 capital budget at this site: $1M (University Park Amenities; CJCC HVAC Grant). It may pay for other work at the site.
What PP&R's record says
Renovation or repair playground that was rated as 4 during playground assessment in 2020
- #3280Top$404.6K2023 estimate
Playground renovation
Wilkes Park · District 1
Playgrounds · Failure risk 20 of 25 · equity 4 of 5 · Condition assessment · requested FY 20/21, 6 years ago · CIP 4394
At risk of closure · playgroundLevy category · playgroundFY 2026–27 capital budget at this site: $875K (Wilkes Headwaters; Wilkes Headwaters Development). It may pay for other work at the site.
What PP&R's record says
Renovation or repair playground that was rated as 5 during playground assessment in 2020
- #3380Top$1M2023 estimate
Renovate sport field
Argay Park · District 1
Sports fields and courts · Failure risk 20 of 25 · equity 4 of 5 · Condition assessment · requested FY 22/23, 4 years ago · CIP 2003
Site named at risk of closureThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Sport fields rated 4 or 5 in condition assessment
- #3480Top$522.6K2023 estimate
Renovate sport field
Floyd Light Park · District 1
Sports fields and courts · Failure risk 20 of 25 · equity 4 of 5 · Condition assessment · requested FY 22/23, 4 years ago · CIP 2011
FY 2026–27 capital budget at this site: $90K (EPCC Roof Repair). It may pay for other work at the site.
What PP&R's record says
Sport fields rated 4 or 5 in condition assessment
- #3580TopNo cost
Sport courts renovation- assessment outcome
Raymond Park · District 1
publishedSports fields and courts · Failure risk 20 of 25 · equity 4 of 5 · Condition assessment · requested FY 23/24, 3 years ago · CIP 4535
FY 2026–27 capital budget at this site: $255.7K (Raymond Pk Play&Sewer). It may pay for other work at the site.
What PP&R's record says
Renovate volleyball court rated badthrough sport court condition assessment in 2023.
- #3680TopNo cost
Renovate Off leash area
Chimney Park · District 2
publishedWalls, fences, plazas and other site features · Failure risk 20 of 25 · equity 4 of 5 · Condition assessment · requested FY 23/24, 3 years ago · CIP 4629
FY 2026–27 capital budget at this site: $4K (Columbia Blvd Bridge @ Chimney Park). It may pay for other work at the site.
What PP&R's record says
Renovate dog off leash area rated 4 or 5 in asset condition assessment
- #3780TopNo cost
Renovate Off leash area
Cherry Park · District 1
publishedWalls, fences, plazas and other site features · Failure risk 20 of 25 · equity 4 of 5 · Condition assessment · requested FY 23/24, 3 years ago · CIP 4631
The Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Renovate dog off leash area rated 4 or 5 in asset condition assessment
- #3880TopNo cost
Replace Electrical Wiring and Lighting
Chimney Park · District 2
publishedSite lighting and electrical · Failure risk 20 of 25 · equity 4 of 5 · Condition assessment · requested FY 24/25, 2 years ago · CIP 4718
FY 2026–27 capital budget at this site: $4K (Columbia Blvd Bridge @ Chimney Park). It may pay for other work at the site.
What PP&R's record says
Problem Statement: The branch wiring and commercial lighting exceeds its useful life. Solution Statement: Replace 11,554 SF of branch wiring with updated commercial led lighting.
- #3980TopNo cost
Restroom South roof replacement
Portland International Raceway · District 2
publishedRoofs · Failure risk 20 of 25 · equity 4 of 5 · Condition assessment · requested FY 24/25, 2 years ago · CIP 4805
Fee-supported site: golf or RacewayLevy category · restroomThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Building condition assessment 24-25: renovate/replace the roof
Score 75 · 21 items, tied
PP&R publishes no order for items with the same score. Listed here oldest request first. 2023 estimates for 9 of 21: $3.5M.
- #4075Top$529.2K2023 estimate
Replace Elephant Barn Roof
Washington Park · District 4
Roofs · Failure risk 25 of 25 · equity 3 of 5 · Work order · requested FY 09/10, 17 years ago · CIP 33
Site named at risk of closureFY 2026–27 capital budget at this site: $50K (WaPk Wayfinding). It may pay for other work at the site.
What PP&R's record says
- Roof is leaking and deteriorated - ongoing leak confirmed in 2026 carpentry roof inspection. - The soffit and facer boards on the southwest corner show signs of rotting and may need to be replaced. - The roof needs replacment. - Need to add sufficient fall protection measures (tie offs, etc.) when roof is replaced. Project update upon condition assessme…
- #4175TopNo cost
Rose Garden Restroom Renovation
Washington Park · District 4
publishedRestrooms · Failure risk 25 of 25 · equity 3 of 5 · Condition assessment · requested FY 14/15, 12 years ago · CIP 602
Site named at risk of closureLevy category · restroomFY 2026–27 capital budget at this site: $50K (WaPk Wayfinding). It may pay for other work at the site.
What PP&R's record says
Renovation of the 1928 restroom B in the Rose Garden parking lot. Roof replacement, seismic upgrades, interior repairs to walls that have suffered water damage, upgrade plumbing, electrical, computer wiring. Project update upon condition assessment outcome 24-25.
- #4275TopNo cost
Renovate main building
Heron Lakes Golf Course · District 2
publishedCommunity centers and other buildings · Failure risk 25 of 25 · equity 3 of 5 · Condition assessment · requested FY 18/19, 8 years ago · CIP 1063
Fee-supported site: golf or RacewayAt risk of closure · roof replacementThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Roof and structure in Bad condition and rated as bad through condition aseesment Project update upon condition assessment outcome 24-25: renovate structure of main building
- #4375TopNo cost
Replace car barns roof
Colwood Property · District 2
publishedRoofs · Failure risk 25 of 25 · equity 3 of 5 · Condition assessment · requested FY 18/19, 8 years ago · CIP 1159
Fee-supported site: golf or RacewayThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
- The roof of Cart Barn is in end of life cycle. Drip edge, fasica and shingles need to replace - This project derived from Building assessment 17-18 and updated 24-25
- #4475Top$154K2023 estimate
Renovate the Roof of Maintenance building
Pier Park · District 2
Roofs · Failure risk 25 of 25 · equity 3 of 5 · Condition assessment · requested FY 19/20, 7 years ago · CIP 1750
Site named at risk of closureThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Fix or replace the Roof that is rated 4 through buildings' assessment 17-18 Project update upon condition assessment outcome 24-25: comprehensive renovation including roof, foundation, and internal. replacment is recommended
- #4575TopNo cost
Renovate the Roof of Restroom building
Plaza Blocks · District 4
publishedRoofs · Failure risk 25 of 25 · equity 3 of 5 · Condition assessment · requested FY 19/20, 7 years ago · CIP 1772
Levy category · restroomThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Fix or replace the Roof that is rated 4 through buildings' assessment 17-18 Project update upon condition assessment outcome 24-25
- #4675Top$12K2023 estimate
Renovate the Roof of Equipment shelter
Roofs · Failure risk 25 of 25 · equity 3 of 5 · Condition assessment · requested FY 19/20, 7 years ago · CIP 4434
Fee-supported site: golf or RacewayThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Fix or replace the Roof that is rated 4 through buildings' assessment 17-18 Project update upon condition assessment outcome 24-25: replace 3 shelters
- #4775Top$231.4K2023 estimate
Secure hanging fiberglass insulation
East Delta Park · District 2
Roofs · Failure risk 25 of 25 · equity 3 of 5 · Work order · requested FY 20/21, 6 years ago · CIP 1725
Site named at risk of closureThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Problem: Fiberglass insulation of tool storage barn attached to naintenance building is falling. Rain water go through the roof, make the fiberglass wet and heavy, and tend to fall Solution1 (Recommended): Fix the roof and replace the insulation Solution2 (Temporary): Use steel strap to hold the fiberglass where there is potentially falling. Straps, scr…
- #4875TopNo cost
Playground renovation
Unnamed location
publishedPlaygrounds · Failure risk 25 of 25 · equity 3 of 5 · Condition assessment · requested FY 20/21, 6 years ago · CIP 1871
Levy category · playgroundWhat PP&R's record says
Renovation or repair playground that was rated as 5 during playground assessment in 2020
- #4975Top$2M2023 estimate
Renovate sport field
Pier Park · District 2
Sports fields and courts · Failure risk 25 of 25 · equity 3 of 5 · Condition assessment · requested FY 22/23, 4 years ago · CIP 2018
Site named at risk of closureThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Sport fields rated 4 or 5 in condition assessment
- #5075Top$50K2023 estimate
Renovate electrical and mechanical equipment
Heron Lakes Golf Course · District 2
Heating, plumbing and other building systems · Failure risk 25 of 25 · equity 3 of 5 · Staff project entry · requested FY 23/24, 3 years ago · CIP 4414
Fee-supported site: golf or RacewaySite named at risk of closureThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Electrical and mechanical equipment’s passed 25 year of service and need to replace.
- #5175Top$50K2023 estimate
Renovate electrical and mechanical equipment
Oaks Pioneer Church and Park · District 4
Heating, plumbing and other building systems · Failure risk 25 of 25 · equity 3 of 5 · Staff project entry · requested FY 23/24, 3 years ago · CIP 4431
The Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Electrical and mechanical equipment’s passed 25 year of service and need to replace.
- #5275Top$50K2023 estimate
Renovate electrical and mechanical equipment
Westmoreland Park · District 4
Heating, plumbing and other building systems · Failure risk 25 of 25 · equity 3 of 5 · Staff project entry · requested FY 23/24, 3 years ago · CIP 4436
Site named at risk of closureFY 2026–27 capital budget at this site: $538.7K (Westmoreland Irrigation Main; Repair WstMrlnd Ntr Ply Logs). It may pay for other work at the site.
What PP&R's record says
Electrical and mechanical equipment’s passed 25 year of service and need to replace.
- #5375TopNo cost
Renovate Off leash area
East Delta Park · District 2
publishedWalls, fences, plazas and other site features · Failure risk 25 of 25 · equity 3 of 5 · Condition assessment · requested FY 23/24, 3 years ago · CIP 4625
Site named at risk of closureThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Renovate dog off leash area rated 4 or 5 in asset condition assessment
- #5475Top$376.8K2023 estimate
Renovate the Roof of Administration building
East Delta Park · District 2
Roofs · Failure risk 25 of 25 · equity 3 of 5 · Condition assessment · requested FY 24/25, 2 years ago · CIP 1730
Site named at risk of closureThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
- Fix or replace the Roof that is rated 4 through buildings' assessment 17-18 - Project update upon condition assessment outcome 24-25- Roof rate 5 and structure 4, and windows and doors 4
- #5575TopNo cost
Replace Single Ply Roofing
Gov Tom McCall Waterfront Park · District 4
publishedRoofs · Failure risk 25 of 25 · equity 3 of 5 · Condition assessment · requested FY 24/25, 2 years ago · CIP 4696
FY 2026–27 capital budget at this site: $550K (Wtrnt Pk Bowl Redvlp; Salmon Street Fountain Electrical). It may pay for other work at the site.
What PP&R's record says
Problem Statement: Roof has standing water in big portions which eventually will lead to failure and leaks. Solution Statement: Replace 3,650 SF of single ply roof and redevelop roof pitch to accommodate proper drainage.
- #5675TopNo cost
Renovate clubhouse
Heron Lakes Golf Course · District 2
publishedCommunity centers and other buildings · Failure risk 25 of 25 · equity 3 of 5 · Condition assessment · requested FY 24/25, 2 years ago · CIP 4776
Fee-supported site: golf or RacewayAt risk of closure · roof replacementThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Condition assessment 24-25: renovate roof and siding of clubhouse
- #5775TopNo cost
Replace Pour In Place play area surface
Thomas Cully Property · District 2
publishedPlaygrounds · Failure risk 25 of 25 · equity 3 of 5 · Work order · requested FY 25/26, 1 year ago · CIP 4871
Levy category · playgroundFY 2026–27 capital budget at this site: $300K (Cully Natv Gath Grdn). It may pay for other work at the site.
What PP&R's record says
Replace failed playground surface (PIP- Pebbleflex Brand) that developing holes and tearing- approx. 2000 sq.ft. Check WO request for detail
- #5875TopNo cost
Replace Poured In Place play surface
Gateway Discovery Park · District 1
publishedPlaygrounds · Failure risk 25 of 25 · equity 3 of 5 · Work order · requested FY 25/26, 1 year ago · CIP 4872
Levy category · playgroundThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Replace failed poured in place (PIP) surface (Pebbleflex Brand) that has developed holes and cracks- approx. 5000 sq.ft. Check WO request for detail
- #5975TopNo cost
Replace Poured In Place play surface
Lents Park · District 1
publishedPlaygrounds · Failure risk 25 of 25 · equity 3 of 5 · Work order · requested FY 25/26, 1 year ago · CIP 4873
Site named at risk of closureLevy category · playgroundFY 2026–27 capital budget at this site: $4.8K (Lents Irrig Replacement). It may pay for other work at the site.
What PP&R's record says
- Replace failed poured in place (PIP) surface (Pebbleflex Brand) that developing holes and cracks- approx. 7000 sq.ft. - Fix grass turf issue around play area - Fix drainage issue in synthetic play area Check WO request for detail
- #6075TopNo cost
Replace wooden retaining wall
Washington Park · District 4
publishedWalls, fences, plazas and other site features · Failure risk 25 of 25 · equity 3 of 5 · Work order · requested FY 25/26, 1 year ago · CIP 4890
Site named at risk of closureFY 2026–27 capital budget at this site: $50K (WaPk Wayfinding). It may pay for other work at the site.
What PP&R's record says
Replace failing wooden retaining wall with dry stack rock wall. Approximate dimension of new wall is 100’ length and 8’ high. Check attached report for more detail.
Score 64 · 29 items, tied
PP&R publishes no order for items with the same score. Listed here oldest request first. 2023 estimates for 18 of 29: $5.6M.
- #6164High$154.8K2023 estimate
Rebuild trail from Airport Way to NE 185th
Big Four Corners Natural Area · District 1
Community centers and other buildings · Failure risk 16 of 25 · equity 4 of 5 · Condition assessment · requested FY 09/10, 17 years ago · CIP 40
The Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Rebuild distressed portions of the trail from Airport Way to NE 185th. Would need to amend the South Shore plan to allow for an upgrade to the trail.
- #6264HighNo cost
Wading Pool Conversion to Splash Pa
Ventura Park · District 1
publishedPools and splash pads · Failure risk 16 of 25 · equity 4 of 5 · Staff project entry · requested FY 09/10, 17 years ago · CIP 170
Growth · SDC-eligibleThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Convert a wading pool to a splash pad at high-ranking site (CIP1). Standard assumptions: flow-through, all ground-spray, avg. 1,300 s.f. wetted area (cap. 50 users) plus spectator zone, in-house design/build. High Priority
- #6364HighNo cost
District Skatepark #4
Ventura Park · District 1
publishedSports fields and courts · Failure risk 16 of 25 · equity 4 of 5 · Staff project entry · requested FY 09/10, 17 years ago · CIP 208
Growth · SDC-eligibleThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Build one 12K sq ft district skatepark that can accommodate 40-100 users. Assumes location already has drinking fountains and RR.
- #6464High$913.2K2023 estimate
Manor House - Retaining Wall
Leach Botanical Garden · District 1
Community centers and other buildings · Failure risk 16 of 25 · equity 4 of 5 · Staff project entry · requested FY 14/15, 12 years ago · CIP 638
The Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Repair retaining wall below the manor. Showing signs of distress.
- #6564HighNo cost
Park Development
SE Division St and SE 150th Ave Property · District 1
publishedNew parks and unnamed future projects · Failure risk 16 of 25 · equity 4 of 5 · Staff project entry · requested FY 18/19, 8 years ago · CIP 891
Levy category · restroomGrowth · SDC-eligibleThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Add amenities, plaza entrance, skate spot, basketball court, flexible lawn space with space for a soccer field, picnic shelter, pollinator garden, restroom, community garden, playground, parking lot, and fenced dog off leash area
- #6664High$23.5K2023 estimate
Repair Nike basketball surface
Harney Park · District 3
Sports fields and courts · Failure risk 16 of 25 · equity 4 of 5 · Work order · requested FY 19/20, 7 years ago · CIP 1054
FY 2026–27 capital budget at this site: $201.2K (Replace Harney Play Structure). It may pay for other work at the site.
What PP&R's record says
The new Nike basketball court surface is peeling and needs repaired before the damage spreads
- #6764High$32.9K2023 estimate
ESPC-II_ Maint Facility - Chimney Park
Chimney Park · District 2
Energy-efficiency retrofits · Failure risk 16 of 25 · equity 4 of 5 · Staff project entry · requested FY 19/20, 7 years ago · CIP 1253
FY 2026–27 capital budget at this site: $4K (Columbia Blvd Bridge @ Chimney Park). It may pay for other work at the site.
What PP&R's record says
Retrocommission all astronomical and mechanical timeclocks to ensure proper operation and correct current time.. FIM Name: 05.00-1399 Retro Commissioning Astronomical & Mech Timeclocks Convert existing lighting to LED technology via a re-lamp approach.. FIM Name: 09.06-1399 Building Interior Lighting LED Conversion Tighten schedules and setpoints to match…
- #6864High$5.1K2023 estimate
ESPC-II_ Maint Facility - SE 136th and Holgate
Maint Facility - SE 136th and Holgate · District 1
Energy-efficiency retrofits · Failure risk 16 of 25 · equity 4 of 5 · Staff project entry · requested FY 19/20, 7 years ago · CIP 1283
Staff site: maintenance yard or officeThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Convert existing lighting to LED technology via a re-lamp approach.. FIM Name: 09.06-0675 Building Interior Lighting LED Conversion
- #6964High$1.1K2023 estimate
ESPC-II_ Maint Facility - SE 136th and Holgate
Maint Facility - SE 136th and Holgate · District 1
Energy-efficiency retrofits · Failure risk 16 of 25 · equity 4 of 5 · Staff project entry · requested FY 19/20, 7 years ago · CIP 1321
Staff site: maintenance yard or officeThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Install a GE control node on each pathway light fixture. Node for parks with <50 fixtures will be model #ELWM18BXXXXAD. Node for parks with >50 fixtures will be model #ELWN08BXXXXAD.. FIM Name: 09.17-0675 Building Exterior Lighting Controls
- #7064High$2K2023 estimate
ESPC-II_ Maint Facility - SE 136th and Holgate
Maint Facility - SE 136th and Holgate · District 1
Energy-efficiency retrofits · Failure risk 16 of 25 · equity 4 of 5 · Staff project entry · requested FY 19/20, 7 years ago · CIP 1348
Staff site: maintenance yard or officeThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Tighten schedules and setpoints to match occupancy and maintain a 5F deadband between occupied heating and cooling setpoints.. FIM Name: 04.01-0675 DDC/Control System Optimization
- #7164High$1.6K2023 estimate
ESPC-II_ Maint Facility - SE 136th and Holgate
Maint Facility - SE 136th and Holgate · District 1
Energy-efficiency retrofits · Failure risk 16 of 25 · equity 4 of 5 · Staff project entry · requested FY 19/20, 7 years ago · CIP 1371
Staff site: maintenance yard or officeThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Convert existing lighting to LED technology via a re-lamp approach.. FIM Name: 09.07-0675 Building Exterior Lighting LED Conversion
- #7264HighNo cost
ESPC-III_Buildings Lighting to LEDs
Portland International Raceway · District 2
publishedEnergy-efficiency retrofits · Failure risk 16 of 25 · equity 4 of 5 · Staff project entry · requested FY 19/20, 7 years ago · CIP 1405
Fee-supported site: golf or RacewayThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
LED conversion for Exterior and Interior Lights
- #7364High$48.2K2023 estimate
ESPC-II_ Maint Facility - SE 136th and Holgate
Maint Facility - SE 136th and Holgate · District 1
Energy-efficiency retrofits · Failure risk 16 of 25 · equity 4 of 5 · Staff project entry · requested FY 19/20, 7 years ago · CIP 1431
Staff site: maintenance yard or officeThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Move the existing CCTV/security station cabinet on E wall of the building into the maintenance supervisor’s office. Cabinet to be mounted so that the top of the cabinet is at the same height as the supervisor’s desk. Propose relocating to the left of the window on the southern wall of the supervisor’s office.. FIM Name: 20.00-0675 Relocate Existing CCTV/S…
- #7464HighNo cost
ESPC-III_Buildings Lighting to LEDs
McCoy Park · District 2
publishedEnergy-efficiency retrofits · Failure risk 16 of 25 · equity 4 of 5 · Staff project entry · requested FY 19/20, 7 years ago · CIP 1523
FY 2026–27 capital budget at this site: $323 (McCoy Drainage). It may pay for other work at the site.
What PP&R's record says
LED conversion for Exterior and Interior Lights
- #7564High$190.7K2023 estimate
Renovate the Structure of Visitor Services building
Leach Botanical Garden · District 1
Seismic and structural · Failure risk 16 of 25 · equity 4 of 5 · Condition assessment · requested FY 19/20, 7 years ago · CIP 1784
The Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Fix or replace the Structure that is rated 4 through buildings' assessment Project update upon condition assessment outcome 24-25
- #7664High$75.6K2023 estimate
Renovate Basketball sport court at Wilkes Park
Wilkes Park · District 1
Sports fields and courts · Failure risk 16 of 25 · equity 4 of 5 · Condition assessment · requested FY 19/20, 7 years ago · CIP 1802
Site named at risk of closureFY 2026–27 capital budget at this site: $875K (Wilkes Headwaters; Wilkes Headwaters Development). It may pay for other work at the site.
What PP&R's record says
Fix or replace the Nike Resurf surface of the court that is rated 4 through courts' assessment
- #7764High$51.2K2023 estimate
Pathway Renovation
Chimney Park · District 2
Paths, trails and stairs · Failure risk 16 of 25 · equity 4 of 5 · Condition assessment · requested FY 20/21, 6 years ago · CIP 1672
FY 2026–27 capital budget at this site: $4K (Columbia Blvd Bridge @ Chimney Park). It may pay for other work at the site.
What PP&R's record says
Replace the damaged pathway, trails and sidewalks that have been rated as 4 and 5 in Pathway assessment
- #7864HighNo cost
Pathway Renovation
Jason Lee Middle School · District 3
publishedPaths, trails and stairs · Failure risk 16 of 25 · equity 4 of 5 · Condition assessment · requested FY 20/21, 6 years ago · CIP 1682
What PP&R's record says
Replace the damaged pathway, trails and sidewalks that have been rated as 4 and 5 in Pathway assessment
- #7964High$54.6K2023 estimate
Pathway Renovation
Argay Park · District 1
Paths, trails and stairs · Failure risk 16 of 25 · equity 4 of 5 · Condition assessment · requested FY 20/21, 6 years ago · CIP 1690
Site named at risk of closureThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Replace the damaged pathway, trails and sidewalks that have been rated as 4 and 5 in Pathway assessment
- #8064High$20.2K2023 estimate
Pathway Renovation
McCoy Park · District 2
Paths, trails and stairs · Failure risk 16 of 25 · equity 4 of 5 · Condition assessment · requested FY 20/21, 6 years ago · CIP 1713
FY 2026–27 capital budget at this site: $323 (McCoy Drainage). It may pay for other work at the site.
What PP&R's record says
Replace the damaged pathway, trails and sidewalks that have been rated as 4 and 5 in Pathway assessment
- #8164High$40.2K2023 estimate
Pathway Renovation
University Park · District 2
Paths, trails and stairs · Failure risk 16 of 25 · equity 4 of 5 · Condition assessment · requested FY 20/21, 6 years ago · CIP 1719
FY 2026–27 capital budget at this site: $1M (University Park Amenities; CJCC HVAC Grant). It may pay for other work at the site.
What PP&R's record says
Replace the damaged pathway, trails and sidewalks that have been rated as 4 and 5 in Pathway assessment
- #8264High$128.3K2023 estimate
Pathway Renovation
Ventura Park · District 1
Paths, trails and stairs · Failure risk 16 of 25 · equity 4 of 5 · Condition assessment · requested FY 20/21, 6 years ago · CIP 1720
The Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Replace the damaged pathway, trails and sidewalks that have been rated as 4 and 5 in Pathway assessment
- #8364High$3.6M2023 estimate
Renovate buildings in Leach Botanical Garden
Leach Botanical Garden · District 1
Community centers and other buildings · Failure risk 16 of 25 · equity 4 of 5 · Staff project entry · requested FY 20/21, 6 years ago · CIP 1821
The Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Renovate Manor house/gift shop, Carriage House, Stone Cabin, and remove Aluminum Bridge Cost details in attached project summary
- #8464High$200.8K2023 estimate
Renovate Basketball sport court at Ed Benedict Park
Ed Benedict Park · District 1
Sports fields and courts · Failure risk 16 of 25 · equity 4 of 5 · Condition assessment · requested FY 23/24, 3 years ago · CIP 1799
Site named at risk of closureFY 2026–27 capital budget at this site: $3K (Repair Ed Benedict Path/Trail/Sidewalk). It may pay for other work at the site.
What PP&R's record says
Fix or replace the Nike Resurf surface of the court that is rated 4 through courts' assessment
- #8564HighNo cost
Provide ADA compliance accessible path of travel
Glenfair Park · District 1
publishedAccessible routes (ADA) · Failure risk 16 of 25 · equity 4 of 5 · 2022 LOS guidance · requested FY 23/24, 3 years ago · CIP 4256
ADA scope2022 LOS guidanceGrowth · SDC-eligibleThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Provide 2 ADA compliance accessible path of travel. For Growth and SDC eligibility, this project will increase the capacity of the park by adding/upgrading circulation trails and pathways.
- #8664HighNo cost
Provide ADA compliance accessible path of travel
Ventura Park · District 1
publishedAccessible routes (ADA) · Failure risk 16 of 25 · equity 4 of 5 · 2022 LOS guidance · requested FY 23/24, 3 years ago · CIP 4315
ADA scope2022 LOS guidanceGrowth · SDC-eligibleThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Provide 1 ADA compliance accessible path of travel. For Growth and SDC eligibility, this project will increase the capacity of the park by adding/upgrading circulation trails and pathways.
- #8764HighNo cost
Workspace- Site configuration and safety
Maint Facility - SE 136th and Holgate · District 1
publishedStaff workspaces · Failure risk 16 of 25 · equity 4 of 5 · Condition assessment · requested FY 23/24, 3 years ago · CIP 4507
Staff site: maintenance yard or officeThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Project components: Improvement Type: Parking, Category: Relcoate storage, Subcategory: NA, Description: Move Tough Shed Storage to Leased faciltiy, Invest#: 675.06 Improvement Type: Parking, Category: Site Configuration, Subcategory: Parking - paving, Description: Pave Visitor/Overflow parking, Invest#: 675.05 Improvement Type: Parking, Category: Site Co…
- #8864HighNo cost
Replace water fountains with a bottle filling stations
Floyd Light Park · District 1
publishedWalls, fences, plazas and other site features · Failure risk 16 of 25 · equity 4 of 5 · Work order · requested FY 24/25, 2 years ago · CIP 4730
Levy category · restroomFY 2026–27 capital budget at this site: $90K (EPCC Roof Repair). It may pay for other work at the site.
What PP&R's record says
Replace the water fountains outside the lobby restrooms and at the pool deck with a bottle filling stations.
- #8964HighNo cost
Inspect and fix foundation
University Park · District 2
publishedSeismic and structural · Failure risk 16 of 25 · equity 4 of 5 · Condition assessment · requested FY 24/25, 2 years ago · CIP 4816
FY 2026–27 capital budget at this site: $1M (University Park Amenities; CJCC HVAC Grant). It may pay for other work at the site.
What PP&R's record says
Building condition assessment 24-25: incline cracks in perimeter foundation could indicate settlement failure. Need special inspection and potential remedy
Score 60 · 98 items, tied
PP&R publishes no order for items with the same score. Listed here oldest request first. 2023 estimates for 81 of 98: $23.3M.
- #9060HighNo cost
Renovate and improve picnic shelter and picnic sit
Columbia Park · District 2
publishedWalls, fences, plazas and other site features · Failure risk 20 of 25 · equity 3 of 5 · Staff project entry · requested FY 04/05, 22 years ago · CIP 530
Site named at risk of closureFY 2026–27 capital budget at this site: $1.8M (Columbia Pool Structural Assessment; Columbia Park Amenities; 1 more). It may pay for other work at the site.
What PP&R's record says
Replace the roof that was rated 4 in condition assessment 24-25 Assess picnic shelter and perform necessary safety upgrades and repairs. Renovate picnic sites as needed. Replaces CIP 1951, projects were split out.
- #9160High$207.8K2023 estimate
Play Area Safety and ADA
DeWitt Park · District 4
Playgrounds · Failure risk 20 of 25 · equity 3 of 5 · Staff project entry · requested FY 09/10, 17 years ago · CIP 173
ADA scopeLevy category · playgroundThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Removal and replacement of existing Wildwood play structures. Wildwood play equipment is no longer manufactured. Structures have outlived their useful life. Add small free play area, per Technical Paper.
- #9260High$267.8K2023 estimate
Renovation of tennis courts
Glenwood Park · District 1
Sports fields and courts · Failure risk 20 of 25 · equity 3 of 5 · Condition assessment · requested FY 09/10, 17 years ago · CIP 190
At risk of closure · courtThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Resurface 2 courts, provide drinking fountain, new benches, fencing and nets/standards. Priority 1
- #9360HighNo cost
Roof repair replacment
Northgate Park · District 2
publishedRoofs · Failure risk 20 of 25 · equity 3 of 5 · Condition assessment · requested FY 09/10, 17 years ago · CIP 504
Site named at risk of closureFY 2026–27 capital budget at this site: $5.7K (Nrthgte Rugby Fld #9). It may pay for other work at the site.
What PP&R's record says
Replace roof on picnic shelter at Northgate Park. Replace shingles, fascia boards, seal. Replaces previous CIP 2287, projects were split out by site. Project update upon condition assessment outcome 24-25- replace roof and renovate the structure
- #9460HighNo cost
Restroom Upgrades
Washington Park · District 4
publishedRestrooms · Failure risk 20 of 25 · equity 3 of 5 · Staff project entry · requested FY 09/10, 17 years ago · CIP 593
Site named at risk of closureLevy category · restroomFY 2026–27 capital budget at this site: $50K (WaPk Wayfinding). It may pay for other work at the site.
What PP&R's record says
Repair restroom at the Holocaust Memorial at Washington Park. Repair exterior surfaces, repaint. Requires lead abatement. Replaces CIP 2286, projects were split out. Updated through condition assessment 24-25
- #9560High$31K2023 estimate
Pool Solar Thermal Installation
Pier Park · District 2
Energy-efficiency retrofits · Failure risk 20 of 25 · equity 3 of 5 · Staff project entry · requested FY 11/12, 15 years ago · CIP 395
Site named at risk of closureThe Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
Installation of a new solar thermal hot water system.
- #9660High$219.9K2023 estimate
Install Boiler
Ida B Wells-Barnett Outdoor Pool · District 4
Heating, plumbing and other building systems · Failure risk 20 of 25 · equity 3 of 5 · Staff project entry · requested FY 14/15, 12 years ago · CIP 644
The Atlas found no FY 2026–27 capital budget line for this site.
What PP&R's record says
1- Project is reliant on pool filter installations. Heated pool water is provided by PPS. Their boilers are inefficient, causing disruptions to pool programming. 2- Steam from PPS during winters has caused a problem of steam entering a very cold climate causing any excess or exhaust of steam to immediately condense in the mechanical room making everythi…
- #9760High$216.5K2023 estimate
Columbia Cottage HVAC and Roof
Columbia Park · District 2
Roofs · Failure risk 20 of 25 · equity 3 of 5 · Condition assessment · requested FY 14/15, 12 years ago · CIP 656
Site named at risk of closureFY 2026–27 capital budget at this site: $1.8M (Columbia Pool Structural Assessment; Columbia Park Amenities; 1 more). It may pay for other work at the site.
What PP&R's record says
- Replace failing furnace. System is at end of life. - Replace the roof as it is in the end of life cycle. Roof condition was detremind through building assessment - Project update following outcome of condition assessment 24-25- fix settlement in the foundation
- #9860High$111.1K2023 estimate
Electrical system replacement
SW Carwash Fountain · District 4
Site lighting and electrical · Failure risk 20 of 25 · equity 3 of 5 · Staff project entry · requested FY 15/16, 11 years ago · CIP 685
What PP&R's record says
Electrical system is unsafe to operate and has been disconnected. Fountain cannot operate until new system is installed. This is for installation of new system.
- #9960High$294K2023 estimate
Restroom Renovation
Columbia Park · District 2
Restrooms · Failure risk 20 of 25 · equity 3 of 5 · Condition assessment · requested FY 15/16, 11 years ago · CIP 857
At risk of closure · restroomLevy category · restroomFY 2026–27 capital budget at this site: $1.8M (Columbia Pool Structural Assessment; Columbia Park Amenities; 1 more). It may pay for other work at the site.
What PP&R's record says
Restroom A: Repair / replace roof , fixtures, lighting, access Renovate the roofs of restroom A and B that were rated 4 in condition assessment 24-25
- #10060High$17.6K2023 estimate
Rose garden Sidewalk
Washington Park · District 4
Paths, trails and stairs · Failure risk 20 of 25 · equity 3 of 5 · Work order · requested FY 17/18, 9 years ago · CIP 965
Site named at risk of closureFY 2026–27 capital budget at this site: $50K (WaPk Wayfinding). It may pay for other work at the site.
What would settle it
Records that would turn this ranking into what gets fixed next
- Funded status for every backlog IDWhich items are in this year's capital budget, the five-year capital plan, the major-maintenance list or the levy project list, matched by project number.
- Current cost for every itemThe estimate PP&R holds now, with its date and basis, so items can be compared on cost as well as need.
- The two ratings behind each failure-risk numberLikelihood and consequence recorded separately, with what each step on the 1-to-5 scales means, and how the equity rating is built.
- How PP&R chooses among tied itemsThe procedure for picking which scored items get funded, and which funding sources may pay for which items.
- Why 304 items have no usable score293 have no score and 11 have a score of 0.